Are we meeting the plan?
Compare work accepted by each sprint-end checkpoint (Wednesday) with the work planned to finish. Flag overdue work, blocked tasks and items waiting for a reviewer. Escalate delays that block the next milestone.
Start on 15 October 2026. Finish the planned work by 14 April 2027. Show progress every month and a working Beth prototype by 13 January 2027.
Kickoff confirmed · 15 October 2026 · 26 weekly sprints · Task instructions remain in the master scope.
The build phase began on 15 October 2026. These are targets, not evidence of completed work. Bernard Chang coordinates the six monthly reviews; each decision needs actual checks and retrievable proof. Capacity, prerequisites, provider access and the RAG effort estimate still need validation. A failed gate holds affected work.
Plan dates: 15 October 2026 – 14 April 2027. The green bars below show the agreed weekly windows. They are planned dates, not a claim that work is complete.
Open the Gantt in Infinity · Open the live board dashboard · See accepted effort over time · Watch the weekly reporting guide
Compare work accepted by each sprint-end checkpoint (Wednesday) with the work planned to finish. Flag overdue work, blocked tasks and items waiting for a reviewer. Escalate delays that block the next milestone.
Every week, total the agreed effort estimates of tasks accepted by a reviewer. Average the last four completed weeks. Count each individual task once; do not add its parent again.
Divide estimated work still open by the recent weekly pace. Check dependencies and team availability before reporting a likely finish date. Unknown estimates or too few completed weeks mean “not enough data”.
Enter weekly totals from Infinity. Count only tasks accepted by a reviewer. Use their agreed effort estimates, not the hours someone has logged. This calculator uses the figures you enter.
| Field | Who updates it | What to enter |
|---|---|---|
| Planned start / Planned finish | Delivery lead | Dates from this plan. Keep the original plan when revising a current due date. |
| Estimated work days | Worker and reviewer | A realistic estimate for this task before the sprint. Enter a positive agreed estimate. Blank or 0 means not estimated; exclude it from pace calculations and hold the finish forecast. |
| Stage | Worker / reviewer | Use the actual stage. Ready for review is not Done. |
| Accepted on | Reviewer | The date the proof was accepted, with the decision in the card. Do not use the last-edit date. |
The website shows the plan. Live work records stay in the private Infinity board. A Gantt shows dates; a weekly chart of accepted work shows pace. We cannot claim a reliable finish forecast before estimates and reviewer acceptance dates are recorded.
01 / The successive objectives
Months are planning blocks: 4, 4, 5, 4, 4 and 5 weeks. Later priorities prepare alongside earlier work, but implementation and acceptance follow the source prerequisites. Testing, expert review and access checks run throughout.
Approve three founder journeys, four service packages, interview records and business-role decisions. Verify the current cloud and prototype baseline.
Product owner, practice lead and access owner approve the journeys, units, bundles, typed interview records and role policy. Cloud isolation and save tests have retrievable evidence.
Try the saved intake and account foundation
Try-it checklist and evidence →Finish secure collection, review/return/conflict handling, specialist eligibility and operator response. Prepare the approved knowledge and pricing inputs.
An expert submits a pack; a named reviewer can return it, reconcile conflicting evidence and hand off approved candidates. Restore and access checks pass.
Submit, return and reconcile an expert contribution
Try-it checklist and evidence →Approve evidence and price drivers; test retrieval, model failures, corrections and quote replay. Connect controlled publication, reports and the first traceable case.
Stakeholders operate the integrated staging prototype themselves across the three approved journeys: setup, monthly compliance and backlog. Inspectable advice, confirmed scope, a repeatable estimate, specialist selection and one saved case pass independent review. A manager previews, publishes and rolls back an approved change.
Operate the working Beth prototype — the midpoint commitment
Try-it checklist and evidence →Prove secure documents, case milestones, human takeover, no-reply tickets, appointments and real email receipts. Admit a bounded pilot only after the week-16 gate.
Week-16 go/hold review passes access, recovery, handoff and appointment checks. Named staff handle the admitted cohort; week 17 begins recording actual scope, effort, rework and quality.
Run a supervised service and appointment journey
Try-it checklist and evidence →Review actual job evidence and correct weaknesses. Approve the broader backlog in week 19, the durable-case plan in week 20 and its contract in week 21. Begin only the approved expanded services and adapters.
Practice lead, product owner and QA accept the measured pilot review and bounded expansion. Required provider accounts, permissions, specialist capacity and durable-case boundaries are ready.
Inspect measured improvements and try an expanded route
Try-it checklist and evidence →Finish expanded channels, one calendar and the Babylon adapter. Prove one durable case workflow, recovery, outcome analytics and the larger operating envelope.
Week 25 proves restart/replay and recovery. In week 26, independent load/failure checks precede the final staged-rollout and rollback decision. Failed critical checks hold the release.
Run the integrated service, interrupt it and recover
Try-it checklist and evidence →Monthly proof of progress
At the end of each month, stakeholders try newly working behaviour on a versioned staging build. Screenshots, planning documents and a recording support the evidence; they do not replace a functioning system. The existing demo is the starting baseline, and each review must identify the new capability delivered since the previous review.
Firm midpoint checkpoint: M03, end of week 13. Beth must have a stakeholder-operated working prototype across the three approved pilot journeys. If it fails, record the result, assign corrective work and hold pilot admission and dependent expansion. Do not silently postpone this commitment or substitute a mockup.
The evidence pack for every month: accessible staging URL, tagged build and change log; sanitised recording and repeatable trial steps; expected-versus-actual results and artifact/record IDs; dated reviewer acceptance or specific return reasons with a named corrective-action owner. Start each pack with Planned / Awaiting review / Accepted / Returned; blank links and checked boxes are not proof of completion.
Use synthetic test businesses for public demonstrations. Keep client identities, private records and sensitive traces in the authorised evidence store; link redacted evidence from the monthly review. Name the build owner and reviewers before the review. QA rehearses before each checkpoint; stakeholder trials and acceptance take place on the Wednesday that closes weeks 4, 8, 13, 17, 21 and 26. Treat a missing demonstration as an unaccepted milestone, record the corrective owner and re-review date, and hold the work that depends on it.
New capability: A deployed account and intake slice, verified against the reusable demo baseline.
Pass criteria: A reviewer can repeat the save/reload and account-isolation checks on the deployed build. Visible screens alone do not pass.
Save as evidence: Build URL/version, redacted save/read and denied-access results, three journey approvals, recorded walkthrough and M01 review decision.
Reviewers: Product owner, practice lead, access owner and QA
Evidence status: Planned requirement; this page does not claim the demonstration has passed.
New capability: The contribution and review loop works with persisted records and an audit trail.
Pass criteria: Stakeholders complete the submit → return → resubmit → reviewed-candidate loop themselves; permissions and history survive reload.
Save as evidence: Redacted contribution/version IDs, review history, conflict decision, private-file/restore results, recorded walkthrough and M02 decision.
Reviewers: Practice lead, knowledge reviewer, operations manager and QA
Evidence status: Planned requirement; this page does not claim the demonstration has passed.
New capability: An integrated frontend and backend turn a founder inquiry into a saved, traceable case.
Pass criteria: Working staging URL and real model, retrieval, quotation and persistence paths; all three agreed journeys run without developer intervention. No canned chat, clickable-only mockup or fabricated case record can satisfy M03. QA/domain reviewers accept the agreed critical checks and candidate evaluation.
Save as evidence: Prototype URL and tagged build, pinned model/prompt/source/rule versions, redacted citation and quote traces, case/retry IDs, evaluation report, stakeholder trial record, recording and dated M03 acceptance.
Reviewers: Product owner, independent CPA/tax reviewer, QA and case operations
Evidence status: Planned requirement; this page does not claim the demonstration has passed.
New capability: The prototype becomes a supervised service with document handling, human ownership and appointment records.
Pass criteria: Staff and founder screens show the same saved case and appointment state. Takeover/no-reply paths and real alert receipts pass; pilot observations begin only after admission approval.
Save as evidence: Redacted case transition log, protected-document tests, takeover/no-reply tickets, appointment/calendar comparison, provider delivery receipts, pilot observation register and M04 decision.
Reviewers: Operations manager, specialist lead, QA and pilot owner
Evidence status: Planned requirement; this page does not claim the demonstration has passed.
New capability: Reviewed pilot results inform a visible improvement and an approved expanded founder route.
Pass criteria: Completed job evidence supports the week-18 review and week-19 expansion decision; the approved change and advanced route work in staging. Plans or dashboards populated with invented pilot outcomes do not pass.
Save as evidence: Anonymised job register and calibration review, improvement release/version and before/after test, expanded-route trial, accepted contract references, recording and M05 decision.
Reviewers: Practice lead, finance owner, product owner, QA and operations
Evidence status: Planned requirement; this page does not claim the demonstration has passed.
New capability: Approved expanded channels and a durable case workflow function with tested recovery and a measured operating limit.
Pass criteria: Accepted provider integrations and recovery checks work end to end. Independent load/failure evidence precedes the week-26 launch decision; passing a demonstration alone never authorises release.
Save as evidence: Redacted provider callbacks/action receipts, pinned workflow/worker versions, recovery and duplicate-event results, load/failure report, rollback rehearsal, recording and M06 decision.
Reviewers: Launch owner, platform/security lead, QA, practice lead and operations
Evidence status: Planned requirement; this page does not claim the demonstration has passed.
Engine handoffs and required proof for each task
02 / Weekly execution
Official kickoff: 15 October 2026. This field previews alternate calendars only.
Each list shows work active that week; the label says when review is due. A multiweek task is one card, carried forward until acceptance. B-codes verify existing prototypes and identify gaps; they do not authorise a full rebuild.
Name the worker/reviewer roles, confirm the three pilot journeys and run the cloud build. Audit reusable prototypes before planning replacement work.
Wednesday acceptance: Named responsibility matrix, journey approval and repeatable build evidence.
Approve countable service units; map interview topics; test private exports, sessions and cloud persistence.
Wednesday acceptance: Service units have clear outputs; cross-account access is denied; a saved draft persists.
Approve the four non-overlapping packages, typed answer schema and specialist credential evidence. Prove save conflicts and configure the cloud AI connection.
Wednesday acceptance: Approved bundle/schema definitions, credential checks and interrupted-save evidence.
Finish interview guidance, profile facts, runtime task profiles, specialist capacity and role policy. Then approve report consent/retention.
Try the saved intake and account foundation
Build owner and QA rehearse before the checkpoint. Stakeholders operate the build on its scheduled checkpoint date; the designated reviewers record acceptance or return with retrievable evidence.
Open demonstration steps and pass criteria →Wednesday acceptance: Contributors know what to submit and why; access and data-use decisions are recorded.
Test private upload and revocation in order; verify matching, prototype reuse and restore. Establish evaluation holdouts, traces and consultation input rules.
Wednesday acceptance: Evidence supports private collection, tested restore, specialist selection and protected test cases.
Approve reviewer transitions, prove scoped MCP actions and consultation confirmation, and complete the cloud demo brief.
Wednesday acceptance: Every approval action has an authorised role; tools and appointment transitions are bounded.
Build assigned review/return; define guided business editors; prove authorised history and final cloud-routing acceptance.
Wednesday acceptance: A contributor can receive a correction request and resubmit; unauthorised history remains inaccessible.
Reconcile expert inputs before publication and rehearse operator status checks and response actions.
Submit, return and reconcile an expert contribution
Build owner and QA rehearse before the checkpoint. Stakeholders operate the build on its scheduled checkpoint date; the designated reviewers record acceptance or return with retrievable evidence.
Open demonstration steps and pass criteria →Wednesday acceptance: Conflicting candidates stay unpublished; an operator can identify and act on a failed service.
Configure the knowledge workspace and approve the bounded pilot facts, PDF/source locators, applicability and price drivers.
Wednesday acceptance: Reviewed evidence and typed pricing drivers are available to the next implementation step.
Test streaming, isolation and failure paths; implement next-question/escalation rules and quantities/bundles from approved versions.
Wednesday acceptance: Confirmed facts survive corrections and model changes; scope and quantities follow approved rules.
Check retrieval/citation support, founder confirmation, release previews and measured pilot capacity.
Wednesday acceptance: Unsupported claims are rejected or qualified; a candidate release is reproducible.
Exercise stale, retired, blocked and conflicting sources; verify quote replay and estimate boundaries.
Wednesday acceptance: Outages preserve an honest escalation path; identical approved inputs replay the quote.
Stakeholders try all three approved founder journeys on the deployed staging build. Prove real model/evidence calls, corrected profiling, rule-based quote replay, one saved case and controlled publication/rollback; retain reproducible candidate evaluation.
Operate the working Beth prototype — the midpoint commitment
Build owner and QA rehearse before the checkpoint. Stakeholders operate the build on its scheduled checkpoint date; the designated reviewers record acceptance or return with retrievable evidence.
Open demonstration steps and pass criteria →Wednesday acceptance: M03: working prototype accepted by week 13. Stakeholder trials, versioned traces, case/retry evidence and independent critical checks pass; a mockup cannot satisfy this checkpoint.
Define document readiness/additional work and prove the website/Telegram inbox bridge.
Wednesday acceptance: A case retains its evidence and scope; the specialist receives the right conversation and ticket.
Verify case states, milestones and human takeover; suppress late bot replies. Rehearse founder/staff UAT.
Wednesday acceptance: One specialist owns the conversation; no duplicate action or bot response appears after takeover.
Verify no-reply tickets, email receipts and appointment reminders in sequence, then run the separate pilot go/hold review.
Wednesday acceptance: Pilot admission is approved only after appointments, alert receipts, access and recovery evidence pass.
Record anonymised actual work, waiting and rework while specialists supervise the admitted cases. Keep changes in candidate review.
Run a supervised service and appointment journey
Build owner and QA rehearse before the checkpoint. Stakeholders operate the build on its scheduled checkpoint date; the designated reviewers record acceptance or return with retrievable evidence.
Open demonstration steps and pass criteria →Wednesday acceptance: Actual scope/version, role hours, quality and exceptions are recorded for completed jobs.
Finish the outcome/calibration review. Decide whether evidence is sufficient for expansion; hold if outcomes are missing.
Wednesday acceptance: Practice lead, finance, QA and product owner record the pilot go/hold decision and unresolved limits.
Prioritise broader journeys/languages and approve channel, calendar and Babylon adapter choices. Confirm provider permissions.
Wednesday acceptance: Bounded expansion and named integration owners are accepted; missing provider access blocks that work.
Approve the durable-case plan and expanded catalogue; begin the selected inbox, calendar and Babylon integrations.
Wednesday acceptance: Approved catalogue and durable-case boundaries; adapter contracts and provider test evidence.
Implement reviewed advanced-founder routes and approve durable states, timers and action receipts. Continue provider adapter work.
Inspect measured improvements and try an expanded route
Build owner and QA rehearse before the checkpoint. Stakeholders operate the build on its scheduled checkpoint date; the designated reviewers record acceptance or return with retrievable evidence.
Open demonstration steps and pass criteria →Wednesday acceptance: Escalations are explicit; durable-case contract and duplicate-safe receipts are accepted.
Finish WhatsApp/LINE, one calendar and the Babylon interface; evaluate expanded language/source/model versions.
Wednesday acceptance: Provider callbacks, identity mapping, consent and duplicate-safe booking synchronisation pass.
Implement the bounded workflow against accepted adapters; extend quoted-versus-actual and delivery analytics.
Wednesday acceptance: Saved versions and action receipts are used; analytics distinguish scope changes from estimate error.
Complete compatible workers, upgrade tests and reviewed outcome reports. Begin the feature freeze and recovery rehearsal.
Wednesday acceptance: Pinned workflow/worker versions and outcome-report evidence are ready for independent recovery tests.
Test restart, replay, duplicate events, missing inputs and operator intervention. Correct critical defects and rerun affected tests.
Wednesday acceptance: The case resumes without duplicate external actions; restore and exception evidence is accepted.
the first three working days: larger-load, access and failure tests. the last two working days: review those results, rollout stages and rollback.
Run the integrated service, interrupt it and recover
Build owner and QA rehearse before the checkpoint. Stakeholders operate the build on its scheduled checkpoint date; the designated reviewers record acceptance or return with retrievable evidence.
Open demonstration steps and pass criteria →Wednesday acceptance: Named reviewers accept the measured operating envelope and release, or record a hold and revised checkpoint.
03 / Make six months realistic
381 planned person-days for the pilot; 575 cumulatively for the broader launch. These include a 20% reserve. The pilot is part of the cumulative figure.
575 ÷ 26 = 22.1 productive person-days per week, about 177 hours, across engineering, QA, platform, product, design and domain review. At four productive days per person per week, that is about 5.5 full-time equivalents across all roles, with uneven demand.
This is capacity arithmetic, not a validated sprint velocity. The 9 October document/RAG changes and each task’s effort must be reconciled before this becomes a staffing commitment. Reserve is held once and released for approved recovery work.
A solo developer or three engineers without supporting reviewers cannot be assumed to meet this plan. With less capacity, keep the supervised pilot as the six-month commitment and move broader expansion.
Parent outcomes require every child and the parent’s independent acceptance evidence. Parent codes are not a numerical scheduling sequence: the source’s child prerequisites control execution. Within-week handoffs are stated in the sprint; a missed handoff moves the downstream task.
The small pilot does not prove an entire annual tax cycle. Retain specialist review and record unobserved seasonal cases explicitly. No critical access, invented-authority, duplicate-action or bot-after-takeover failure is acceptable in the agreed release suite.
04 / Turn the plan into working cards
Present the weekly story: use the management dashboard mockup to explore accepted delivery, pace, blockers and monthly decisions. It includes an example review and the dated board-readiness assessment. Sample figures are clearly labelled; this is not a live Infinity dashboard.
The plan maps all 130 source references: 98 scheduled work items and guides, plus 32 parent outcomes. The matching planned start and finish dates are recorded on the existing Infinity cards. Existing assignments, due dates, checkmarks and work progress remain unchanged.
One Beth delivery board, several ways to read it. The folders hold records; the tabs are saved views of those records. A dashboard panel or chart summarises a selection of them. Changing a task can update several views automatically. View names and filters were checked on 17 October 2026.
Start with Dashboard ↗, then Milestones & weekly sprints ↗. Deal with blockers and waiting reviews. At the monthly checkpoint, record a dated pass, return or hold on the milestone card ↗.
Open your exact work-package card and its source link. Developers manage daily steps; experts supply or check the required facts. Reviewers verify the result against the source’s done rule. Use personal logs for effort detail and the package card for delivery proof.
| View | Question it answers | What it actually shows | Your next action |
|---|---|---|---|
| Dashboard ↗ | Project health at a glance | Its panels show the delivery timeline, a count of reported activity entries by workstream, and blocked work. The pie is an activity-entry count, not hours or percentage complete. | Bernard starts here, then opens the underlying task before making a decision. |
| Project Overall ↗ | Find a record across the board | A register grouped by Workstream. It can contain delivery tasks, milestones and activity records. Counts depend on filters and whether parent/child records are expanded. | Search the exact code, such as P04.2; check Work item type before interpreting the row. |
| Milestones & weekly sprints ↗ | Agree and follow the week’s work | Beth records grouped by Current Sprint, Next Sprint or an unset selection; sorted by Planned finish. A blank sprint selection means no rolling bucket was recorded. | Use the dated S01–S26 plan to confirm the actual week. Keep the same card when work carries over; change its due date only by agreement. |
| Ready to Claim ↗ | Find candidate work to take on | The current filter includes Project task/Work package, To Do/In Progress/Upcoming, Completed unchecked, and Planned start = This Week. It does not test for an empty assignee or accepted prerequisites. | Check the current assignee first. Confirm the owner, reviewer, inputs and sprint commitment before claiming; an item appearing here is not proof that it is free to take. |
| Ready for review ↗ | Decide whether submitted work passes | Filters Stage = Ready for review. Apply to Subitems is currently off, so it is not a complete audit of every child package. | Reviewer opens the relevant child cards, follows the evidence and accepts or returns the result. A quiet queue does not prove every child has been reviewed. |
| Blocked work ↗ | Get a decision or missing input | Filters Stage = Blocked. Apply to Subitems is currently off. The dashboard embeds this view too. | Record what is missing, who can resolve it, the next decision date and the milestone affected. Check child cards for additional blockers. |
| Project timeline ↗ | See when delivery work is planned | Uses Planned start and Planned finish. Its current Work Area filter covers backend/integration, customer interface, service knowledge/quotation and QA/reporting. Some guides, reviews or other areas can be absent. | Use it to spot overlaps and delayed handoffs. Check Undated Items and use the complete website sprint plan plus monthly review timeline for the full picture. A bar is a planned window, not accepted progress. |
| Accepted effort over time ↗ | Measure work that has actually passed review | A line chart sums Estimated work days by Accepted on. Filters: Work package/Delivery guide, Stage Done, positive estimate, acceptance after 14 Oct 2026; subitems included. Parent outcomes and activity logs are excluded. | Worker/reviewer agree the estimate before the sprint; reviewer records the acceptance date and proof. Total accepted estimates per sprint to measure pace. Hours logged do not feed this chart. Empty data means no qualifying record, not zero work performed. |
| Columns ↗ | Find records missing a type | Despite the general name, it filters Work item type = empty and groups by that field. It is a housekeeping view rather than the delivery-stage board. | Classify a record before using it in reports. An empty view means the current filter found no unclassified records; it says nothing about project completion. |
These are the saved settings observed during this review. If a colleague changes them later, read Filter, Group and the selected date fields before interpreting a total. No existing chart or filter was reconfigured for this guide.
| Folder | Use it for | How to read the current tab |
|---|---|---|
| Existing Prototype Work ↗ | B packages: verify reusable conversation, interface, intake and service-record work. | All Backlog Tasks; currently grouped by Work Area. |
| Cloud release ↗ | D packages: deployment, access, persistence, AI connection, recovery and cloud handover. | By stage; grouped by Stage. |
| Pilot readiness ↗ | P packages: service definitions, reviewed knowledge, profiling, quotes, cases, appointments and pilot checks. | By stage is the tab name; the observed grouping is Work Area. |
| Later enhancements ↗ | L packages: approved expansion, channel/provider connections, durable cases and broader release. | By stage is the tab name; the observed grouping is Workstream. Follow the plan’s approval gates before starting later work. |
| Delivery and Traceability Guides ↗ | G packages: who owns work, how to report it and how evidence connects to acceptance. | Columns is this folder’s table-tab name; use G01/G02 as operating rules. |
| Clarence ↗ | Personal activity journal. | List table; log the activity date, effort and package reference. The delivery task remains the record of acceptance. |
| Jasmin ↗ | Personal activity journal. | List table; coordination/review activity still needs a link to the affected task or decision. |
| Cyrill John ↗ | Personal activity-journal location. | List table; no populated activity row was visible in this review. |
| Jemae Lyn ↗ | Personal activity journal. | List table; retain daily detail here if useful, then put the weekly outcome and evidence on the delivery card. |
| Sample ↗ | Example records for learning the activity-log format. | Contains Task Logging records. The activity pie has no folder exclusion in its inspected filter, so do not assume examples are excluded from its count. |
| Monthly milestones ↗ | M01–M06 stakeholder demonstrations and decisions; Bernard Chang initially owns the reviews. | Table plus Monthly acceptance timeline. Each card has its source checklist, required evidence and a separate Acceptance evidence field. |
Open the monthly acceptance timeline ↗ for the six review windows. The implementation Gantt and review Gantt answer different questions: when the work runs, and when its combined result must be demonstrated.
Three different measures: activity-entry counts show how many reports were logged; hours show reported effort; accepted estimated work days show delivery pace. None of those alone establishes that a monthly milestone passed.
Current queue entries are live work records. For example, D04 was still marked Blocked in this review; that is a request for the owner to verify and update evidence, not a new technical test of the deployed AI service.
For P04.2 · retrieval and citation checks, read the source’s required proof, the system handoff and the S11 checkpoint. The worker attaches the tested version and expected/actual results in Infinity. The reviewer records acceptance. P04 then uses its required child evidence plus the combined feature test; M03 uses the accepted capability in its stakeholder demonstration. An activity log saying “worked on citations” supplies effort context, but cannot replace that chain.
Watch the daily, weekly and monthly operating guide: a narrated walkthrough of the cards, chart relationships and management presentation.
Management presentation: open the separate Weekly management review dashboard in Infinity. Live panels use the board’s task records. The dashboard is available, and the weekly snapshot register and chart are prepared. Automatic weekly capture and forecasts are not yet active. Use the reporting-method reference for the measurement rules and visual example.
Delivered: what works and the version. Evidence: retrievable, redacted URL and expected/actual result. Remaining or blocked: the missing work or decision, its owner and target date. Next: the next action and expected review date. The reviewer adds a dated accept/return decision; use Acceptance evidence for its proof link. Keep confidential evidence in the private board or an access-controlled location.
Review a delivered work package step by step → Record the actual result, proof and accept/return/hold decision before closing the same Infinity card.
Closing rule: Upcoming → To Do → In Progress → Ready for review → Done is the normal path; Blocked records an interruption. Done requires reviewer acceptance, not just checked boxes. When a review fails, record the reason and return the same task for correction. No daily management report is required; developers can retain the activity-log format their team uses.
Use the M01–M06 records in the Monthly milestones folder. Bernard Chang is the initial accountable owner and reviewer of each monthly decision; the practice, product, security and QA roles named in each gate still provide their checks. Each record links to its exact demonstration checklist and states the required proof. Add actual build URL/version, trial result, recording and dated acceptance or return when available. Its Stage reflects evidence review, not the calendar. Return failed work to the relevant source card; do not duplicate implementation tasks.
Open the weekly sprint view ↗ · Open M01–M06 milestone reviews ↗
The source plan defines done. Each Infinity card records the worker, reviewer, weekly report, source link and actual acceptance proof. Put the dated decision and retrievable proof URL in the Acceptance evidence field when it exists; keep the source-plan link separate. A source link is not acceptance proof. See the monthly acceptance timeline ↗
The CSV is a planning/mapping file. Match existing items by package code and review field mappings before import; a blind import can create duplicates. It is not an automatic board synchronisation or a named assignment.
You do not need to read code. Follow the actions, compare what happened with the expected result, then submit a decision and evidence the programmer can act on.
M01 demonstration and full milestone conditions · Review and acceptance rules · Infinity reporting guidance
QA means the tester or quality reviewer. All 130 source references have review instructions: 84 work packages, 12 prototype checks, 32 parent outcomes and two operating guides. Prepared instructions are not proof that a planned feature is built or accepted. Bernard Chang coordinates M01, and the named product, practice, access and technical reviewers supply the required approvals. Sign in as the assigned reviewer to save observations and send the review to the matching Infinity card. The assigned independent technical or domain reviewer supplies a same-version sign-off from a separate account. The worksheet guides your testing; it does not itself run the application tests or mark parent features or milestones Done.
2 min 10 sec · Open your assigned work, try the checks, attach proof, submit a decision and follow the handoff to Infinity.
Use approved test environments and fake data. Never enter passwords, session tokens or real client records in observations. Uploaded evidence and saved reviews require an assigned Beth account; use redacted proof and approved private recording links.
Example return: “After signing back in, the October draft showed 0 entries instead of the 50 I saved. Screenshot attached. Please restore the saved values and return a new build for retest.”
Search the full catalogue below by task code, topic, planned month or review type. Each checklist gives the action, expected result, evidence and responsible role. A signed-in assignment enables protected uploads and automatic comments on the existing Infinity card. Task stages and monthly milestone decisions remain with the authorised team.
Loading the guided checks…
05 / Every task remains traceable
130 source references
Open the step-by-step review and evidence form for P01
Plan: 15 Oct 2026 – 04 Nov 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P01.1
Plan: 15 Oct 2026 – 21 Oct 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P01.2
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: P01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P01.3
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: P01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P02
Plan: 22 Oct 2026 – 11 Nov 2026. Finish first: P01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P02.1
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: P01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P02.2
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: P02.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P02.3
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: P02.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P03
Plan: 19 Nov 2026 – 09 Dec 2026. Finish first: P02.3 · P16
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P03.1
Plan: 19 Nov 2026 – 25 Nov 2026. Finish first: P02.3 · P16
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P03.2
Plan: 26 Nov 2026 – 02 Dec 2026. Finish first: P03.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P03.3
Plan: 03 Dec 2026 – 09 Dec 2026. Finish first: P03.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P04
Plan: 10 Dec 2026 – 06 Jan 2027. Finish first: P01.1 · P03.3 · P14.2
System connections: I04 · I05 · I06 · I07 · Checks: T03 · T04 · T05 · T06
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P04.1
Plan: 10 Dec 2026 – 16 Dec 2026. Finish first: P01.1 · P03.3
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P04.2
Plan: 24 Dec 2026 – 30 Dec 2026. Finish first: P04.1 · P14.2
System connections: I06 · I07 · Checks: T05
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P04.3
Plan: 31 Dec 2026 – 06 Jan 2027. Finish first: P04.2
System connections: I05 · I06 · I07 · Checks: T03 · T04 · T06
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P05
Plan: 05 Nov 2026 – 30 Dec 2026. Finish first: P01.2 · P02.2 · P04.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P05.1
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: P01.2 · P02.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P05.2
Plan: 17 Dec 2026 – 23 Dec 2026. Finish first: P05.1 · P04.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P05.3
Plan: 24 Dec 2026 – 30 Dec 2026. Finish first: P05.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P06
Plan: 10 Dec 2026 – 06 Jan 2027. Finish first: P01.2 · P03.3 · P01.3 · P05.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P06.1
Plan: 10 Dec 2026 – 16 Dec 2026. Finish first: P01.2 · P03.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P06.2
Plan: 17 Dec 2026 – 23 Dec 2026. Finish first: P06.1 · P01.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P06.3
Plan: 31 Dec 2026 – 06 Jan 2027. Finish first: P06.2 · P05.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P07
Plan: 29 Oct 2026 – 18 Nov 2026. Finish first: P01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P07.1
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: P01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P07.2
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: P07.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P07.3
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: P07.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P08
Plan: 07 Jan 2027 – 27 Jan 2027. Finish first: P06.3 · P07.3 · P16
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P08.1
Plan: 07 Jan 2027 – 13 Jan 2027. Finish first: P06.3 · P07.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P08.2
Plan: 14 Jan 2027 – 20 Jan 2027. Finish first: P08.1 · P16
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P08.3
Plan: 21 Jan 2027 – 27 Jan 2027. Finish first: P08.1 · P08.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P09
Plan: 14 Jan 2027 – 03 Feb 2027. Finish first: P07.3 · P08.1 · P16 · P07.2 · P13
System connections: I08 · Checks: T07
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P09.1
Plan: 14 Jan 2027 – 20 Jan 2027. Finish first: P07.3 · P08.1 · P16
System connections: I08
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P09.2
Plan: 21 Jan 2027 – 27 Jan 2027. Finish first: P09.1 · P07.2
System connections: I08 · Checks: T07
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P09.3
Plan: 28 Jan 2027 – 03 Feb 2027. Finish first: P09.2 · P13
System connections: I08
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P10
Plan: 26 Nov 2026 – 13 Jan 2027. Finish first: P03.1 · P01.3 · P16 · P03.3 · P04.1 · P06.2 · P04.3
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P10.1
Plan: 26 Nov 2026 – 02 Dec 2026. Finish first: P03.1 · P01.3 · P16
System connections: I04
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P10.2
Plan: 24 Dec 2026 – 30 Dec 2026. Finish first: P10.1 · P03.3 · P04.1 · P06.2
System connections: I04
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P10.3
Plan: 07 Jan 2027 – 13 Jan 2027. Finish first: P10.2 · P04.3
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P11
Plan: 12 Nov 2026 – 17 Feb 2027. Finish first: P01.1 · P01.2 · P02.3 · P10.2 · P04.2 · P05.3 · P06.3 · P07.3 · P15.2 · P08.3 · P15.3 · D07.3
System connections: I07
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P11.1
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: P01.1 · P01.2 · P02.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P11.2
Plan: 07 Jan 2027 – 13 Jan 2027. Finish first: P11.1 · P10.2 · P04.2 · P05.3 · P06.3 · P07.3 · P15.2
System connections: I07
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P11.3
Plan: 04 Feb 2027 – 17 Feb 2027. Finish first: P11.2 · P08.3 · P15.3 · D07.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P12
Plan: 18 Feb 2027 – 03 Mar 2027. Finish first: P11.3 · P14
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P12.1
Plan: 18 Feb 2027 – 24 Feb 2027. Finish first: P11.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P12.2
Plan: 18 Feb 2027 – 24 Feb 2027. Finish first: P11.3 · P14
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P12.3
Plan: 25 Feb 2027 – 03 Mar 2027. Finish first: P12.1 · P12.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P13
Plan: 05 Nov 2026 – 13 Jan 2027. Finish first: P04 · P06 · P16
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P13.1
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: P01 · P16.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P13.2
Plan: 07 Jan 2027 – 13 Jan 2027. Finish first: P13.1 · P04 · P06
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P13.3
Plan: 26 Nov 2026 – 02 Dec 2026. Finish first: P13.1 · P16.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P14
Plan: 05 Nov 2026 – 06 Jan 2027. Finish first: P01 · P04 · P16.1
System connections: I01 · I02 · I03 · I09 · Checks: T01 · T02 · T09
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P14.1
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: P01
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P14.2
Plan: 17 Dec 2026 – 23 Dec 2026. Finish first: P14.1 · P04.1 · D04.1
System connections: I01 · I02 · I03 · Checks: T01 · T02
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P14.3
Plan: 19 Nov 2026 – 25 Nov 2026. Finish first: P14.1 · P16.1
System connections: I09 · Checks: T09
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P15
Plan: 12 Nov 2026 – 03 Feb 2027. Finish first: P08 · P09 · P14 · P16
System connections: I03 · I05 · I10
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P15.1
Plan: 28 Jan 2027 – 03 Feb 2027. Finish first: P08.1 · P17.2 · P09.2
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P15.2
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: P14.1 · D01.1
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P15.3
Plan: 24 Dec 2026 – 30 Dec 2026. Finish first: P14.2 · P15.2 · P16
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P16
Plan: 05 Nov 2026 – 18 Nov 2026. Finish first: P01 · D02 · D03
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P16.1
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: P01 · D02
System connections: I01
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P16.2
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: P16.1 · P01
System connections: I06
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P16.3
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: P16.1 · P16.2 · P13.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P17
Plan: 12 Nov 2026 – 03 Feb 2027. Finish first: P07 · P16.1 · P08.1
System connections: I09
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P17.1
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: P07.2 · P16.1
System connections: I09
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P17.2
Plan: 19 Nov 2026 – 25 Nov 2026. Finish first: P17.1 · P07.3
System connections: I09
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for P17.3
Plan: 28 Jan 2027 – 03 Feb 2027. Finish first: P17.2 · P15.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D01
Plan: 15 Oct 2026 – 02 Dec 2026. Finish first: D02.1 · D02.2 · D02.3 · D03.1 · D03.2 · D03.3 · D04.2 · D04.3 · D06.1 · D06.2 · D06.3 · D07.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D01.1
Plan: 15 Oct 2026 – 21 Oct 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D01.2
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: D01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D01.3
Plan: 26 Nov 2026 – 02 Dec 2026. Finish first: D01.1 · D01.2 · D02.1 · D02.2 · D02.3 · D03.1 · D03.2 · D03.3 · D04.2 · D04.3 · D06.1 · D06.2 · D06.3 · D07.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D02
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: D01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D02.1
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: D01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D02.2
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: D01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D02.3
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: D01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D03
Plan: 22 Oct 2026 – 04 Nov 2026. Finish first: D01.1 · D02.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D03.1
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: D01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D03.2
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: D03.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D03.3
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: D03.1 · D02.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D04
Plan: 29 Oct 2026 – 11 Nov 2026. Finish first: D01.1 · D02.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D04.1
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: D01.1 · D02.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D04.2
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: D04.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D04.3
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: D04.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D05
Plan: 29 Oct 2026 – 18 Nov 2026. Finish first: D03.1 · D03.3 · D02.1
System connections: I10 · Checks: T10
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D05.1
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: D03.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D05.2
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: D05.1 · D03.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D05.3
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: D05.2 · D02.1
System connections: I10 · Checks: T10
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D06
Plan: 29 Oct 2026 – 18 Nov 2026. Finish first: D01.1 · D01.2 · D03.3 · D04.2 · D03.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D06.1
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: D01.1 · D01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D06.2
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: D03.3 · D04.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D06.3
Plan: 05 Nov 2026 – 11 Nov 2026. Finish first: D01.1 · D03.2 · D03.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D07
Plan: 19 Nov 2026 – 03 Feb 2027. Finish first: D06.1 · D06.2 · D06.3 · D01.3 · D05.3 · P11.2 · P15.1 · P15.3 · P16 · P17
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D07.1
Plan: 19 Nov 2026 – 25 Nov 2026. Finish first: D06.1 · D06.2 · D06.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D07.2
Plan: 03 Dec 2026 – 09 Dec 2026. Finish first: D01.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for D07.3
Plan: 28 Jan 2027 – 03 Feb 2027. Finish first: D01.3 · D05.3 · D07.2 · P11.2 · P15.1 · P15.3 · P16 · P17
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L01
Plan: 25 Feb 2027 – 17 Mar 2027. Finish first: P12.1 · P11.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L01.1
Plan: 25 Feb 2027 – 03 Mar 2027. Finish first: P12.1 · P11.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L01.2
Plan: 04 Mar 2027 – 10 Mar 2027. Finish first: L01.1 · P04.3 · P05.3 · P06.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L01.3
Plan: 11 Mar 2027 – 17 Mar 2027. Finish first: L01.2 · P11.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L02
Plan: 25 Feb 2027 – 17 Mar 2027. Finish first: P12.2 · P14.3 · P17
System connections: I09 · Checks: T08
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L02.1
Plan: 25 Feb 2027 – 17 Mar 2027. Finish first: P12.2 · P09.3 · P16.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L02.2
Plan: 25 Feb 2027 – 17 Mar 2027. Finish first: P12.2 · P17.3 · P14.3
System connections: I09 · Checks: T08
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L02.3
Plan: 25 Feb 2027 – 17 Mar 2027. Finish first: P12.2 · P07.3 · P08.3 · P14.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L03
Plan: 04 Mar 2027 – 07 Apr 2027. Finish first: P12.3 · P08 · L02
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L03.1
Plan: 04 Mar 2027 – 10 Mar 2027. Finish first: P12.3 · P08.3 · P13.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L03.2
Plan: 18 Mar 2027 – 31 Mar 2027. Finish first: L03.1 · L02.2 · L02.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L03.3
Plan: 01 Apr 2027 – 07 Apr 2027. Finish first: L03.2 · D05.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L04
Plan: 18 Mar 2027 – 14 Apr 2027. Finish first: L01 · L02 · L03 · P12.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L04.1
Plan: 18 Mar 2027 – 31 Mar 2027. Finish first: P11.3 · L01.1 · L02.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L04.2
Plan: 08 Apr 2027 – 14 Apr 2027. Finish first: L01.3 · L02.1 · L03.3 · P15.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for L04.3
Plan: 08 Apr 2027 – 14 Apr 2027. Finish first: L04.1 · L04.2 · L03.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B01
Plan: 15 Oct 2026 – 04 Nov 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B01.1
Plan: 15 Oct 2026 – 21 Oct 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B01.2
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: B01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B01.3
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: B01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B02
Plan: 22 Oct 2026 – 18 Nov 2026. Finish first: B01.1 · B01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B02.1
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: B01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B02.2
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: B02.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B02.3
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: B02.2 · B01.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B03
Plan: 22 Oct 2026 – 18 Nov 2026. Finish first: B01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B03.1
Plan: 22 Oct 2026 – 28 Oct 2026. Finish first: B01.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B03.2
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: B03.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B03.3
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: B03.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B04
Plan: 15 Oct 2026 – 18 Nov 2026. Finish first: B01.1 · B03.1 · B01.3 · B02.3 · B03.3
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B04.1
Plan: 15 Oct 2026 – 21 Oct 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B04.2
Plan: 29 Oct 2026 – 04 Nov 2026. Finish first: B01.1 · B03.1
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for B04.3
Plan: 12 Nov 2026 – 18 Nov 2026. Finish first: B01.3 · B02.3 · B03.3 · B04.2
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for G01
Plan: 15 Oct 2026 – 21 Oct 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.
Open the step-by-step review and evidence form for G02
Plan: 15 Oct 2026 – 21 Oct 2026. Finish first: Check the inputs listed in the task instructions.
System connections: Use the linked task instructions.
Read the full task and required proof · Check this task’s system connections · Open the live Infinity card
Update work status and reports in Infinity. The agreed plan dates do not mean the task has started or been accepted.