00:00 — A clear path from scope to finished work
Welcome to the Beth delivery orientation. The aim is to make the whole project understandable: what is planned, who should do it, and what proves the work is finished. Follow one continuous path. Start with a founder benefit, find its definition in the scope, assign a bounded work package in Start Infinity, collect the evidence, and have the designated reviewer accept it. The scope explains the work; the board records its execution.

00:31 — Start with the reading path for your role
On the master scope page, choose the reading path for your role. Technical contributors start with the engine responsibilities and evidence pipeline. Specialists start with services, interview inputs, and professional review. Managers start with the release boundary, responsibilities, and delivery breakdown. The visual scope helps connect a screen or feature to the work behind it. The user guide teaches someone how to use Beth. They serve different purposes.

00:59 — Read P04 and P04.2 differently
A code such as P zero four is the parent outcome: publish applicable knowledge with verified citations. P zero four point two is a smaller package: verify retrieval and citation support. Every package has a stable source anchor. Use that exact link when discussing the work, rather than sending colleagues to the top of a long page. The current source is a draft. Publication alone does not mean the scope, staffing, or delivery has been approved.

01:32 — Five families, different purposes
There are five code families. B records existing prototype work; it does not mean production acceptance. D covers cloud verification, access, saved data, AI, recovery, user journeys, and release handover. P covers readiness for the supervised pilot. L covers the broader launch after pilot evidence. G contains the ownership, reporting, and traceability guides. There are one hundred and thirty references across thirty four parent tasks and guides. The codes identify work; they are not a calendar or proof that anything is already done.

02:14 — P01–P10: design the service and deliver it
Read the pilot families as a service chain. P one defines journeys and the service catalogue. P two connects interview questions to decisions. P three reviews submissions. P four governs knowledge and citations. P five handles profiling and confirmed scope. P six handles repeatable pricing. P seven verifies specialists. P eight carries the case and additional work. P nine supports human takeover. P ten gives business staff controlled editing, preview, publication, and rollback. These are connected responsibilities, not ten separate software products.

02:54 — P11–P17 and the expansion boundary
P eleven evaluates the pilot. P twelve prepares the broader backlog. P thirteen covers reports, consent, and history. P fourteen covers conversation, model routing, and authorised tool actions. P fifteen covers alerts and observability. P sixteen covers permissions and private documents. P seventeen covers consultations. Broader work then expands journeys and language, adds channels and calendar adapters, makes a multi day case durable, and proves wider operating scale. A working demo helps explain the product, but does not demonstrate that the proposed production engines are all installed.

03:37 — One definition, two places to use it
Here is the translation into Start Infinity. A parent outcome becomes one parent card. A child package becomes its own assignable work package card. The numbered source steps become native checklist entries. The description holds the result, inputs, boundaries, review requirements, exact source anchor, and source revision. Infinity holds the live assignees, reviewer, stage, due date, reports, checked steps, and evidence. Existing mapping records show these cards were created previously. The illustrated card here explains the agreed format, not today’s live assignments or progress.

04:14 — Read a card from top to bottom
Take P zero four point two as the example. The title begins with the stable code, then a concrete action. The worker role is AI or data engineer. The reviewer is the knowledge reviewer and quality team. The result says that answers must cite the actual applicable support. Inputs include approved facts and the runtime contract. The checklist describes retrieval, retained source identifiers, claim support checks, unsupported claims, and difficult source cases. A named person must fill the assignment field. A role name in the source is not a personal assignment.

04:53 — Make the dependencies clickable and usable
Use the dependency codes to open their exact source sections. Before starting P zero four point two, check the accepted outputs of P zero four point one and P fourteen point two. A dependency means an input or decision is needed; it does not mean copy the whole parent into the schedule. Parent dependency lists also contain child completion requirements. Read prerequisites and required children separately. Child and parent checklists do not automatically synchronise. A completed child still needs the parent outcome to be reviewed.

05:30 — Approve the assignment before starting
Before moving a package to To Do, apply the assignment gate. Name the worker and reviewer. Confirm the approved source revision and available inputs. Validate the effort and agree the checkpoint. Define the evidence that will be reviewed. These are practical checks, not extra paperwork. If a required service definition or source passage is missing, the engineer cannot solve the business uncertainty by coding around it. Record the decision and its owner. Begin only the work whose inputs are ready.

06:07 — Parallel work, connected by evidence
A useful planning pattern is to work in waves. First define journeys, service units, and permissions. Prepare the knowledge, runtime rules, and reference cases in parallel where inputs allow. Then connect profiling, estimates, and specialist fit. Complete cases, booking, human handoff, and notifications. Finally evaluate the whole journey, rehearse recovery, and approve rollout. These waves are a planning aid, not an approved dependency schedule. Check the child level prerequisites, resolve cycles or inconsistent references, and agree actual dates with the team.

06:43 — Effort, elapsed time and draft conflicts
Person days measure combined effort, not the number of days on the calendar. Several roles can work at once, while approvals can create waiting time. Do not count the parent, children, and workstream allocation as three separate budgets. Keep reserve once, and treat broader launch totals as cumulative. The current source also needs reconciliation: the evaluation section proposes a larger test suite than the older P eleven checklist, and the knowledge refinement requires effort revalidation. Resolve those differences before approving the baseline. A video cannot turn a draft into an agreed plan.

07:26 — Keep execution visible in Infinity
During execution, keep the card stage and report current. To Do means the inputs and assignment are ready. In progress means work is being produced. Blocked means an exact input or decision is preventing a specific step. For a review handoff, provide the versioned deliverable and checks. Acceptance comes from the designated reviewer. Use the actual Stage options configured on the board; these labels illustrate the workflow. Checklist ticks show progress, but they do not establish that a feature is safe or accepted.

08:02 — Write a report someone can act on
A useful latest report is specific. For example: retrieval checks completed in build R eighteen, with a redacted trace linked. The result is that the approved passage supports the tested claim. The blocker is a conflicting effective date in test case K zero seven. The decision needed is a domain reviewer’s applicability ruling. The next action is to rerun the fixed suite. Record the agreed checkpoint and the actual last reported time. This is a model report, not evidence that this test has really passed.

08:39 — Acceptance needs evidence, then a decision
For acceptance, attach the exact artifact version, expected and actual results, and retrievable evidence. Redact private client data. The reviewer records a dated decision, including any corrections. Test failures, access failures, missing citations, and provider outages need their own evidence, not just a screenshot of the happy path. Accept the parent only when the required children, the feature outcome, and the parent’s original checklist all pass. A card marked complete without review is a progress claim, not an acceptance record.

09:14 — Pilot first; expand from measured results
The supervised pilot is a bounded release, with staff monitoring cases and reviewing important decisions. Its proposed boundary is three journeys, four packages, and approximately twelve to fifteen validated service items. Onboard specialists, train operators, test the full journey and failures, and name release and recovery owners. Review the pilot evidence before expanding to more journeys, channels, or durable case automation. The gate is demonstrated readiness and explicit release approval, not the date on a roadmap.

09:50 — Change the definition without losing history
When a rule, engine, or scope changes, update and review the source definition first. Identify affected package codes and tests, compare the changed definitions with their cards, and preserve assignments, progress, reports, and evidence. Retire removed work explicitly rather than deleting its history. A source link does not automatically synchronise the board. The source records an explicit reference update, not a background synchronisation service. Existing checklist progress also needs a conscious review when steps change.

10:25 — Your first working session
For your first working session, choose one founder outcome, such as answering with a reliable source. Open its parent and child source anchors. Resolve the draft definition and prerequisites. Find the matching card in Infinity by its code, confirm the description and checklist, then assign a worker, reviewer, and checkpoint. Produce the agreed evidence and request acceptance. Managers make decisions and unblock work; specialists validate business meaning; engineers implement and prove behaviour. That is how this collection of documents becomes an organised delivery system.